The suggested setting and connection plan for a typical tank
battery is shown in Figs. 1 I .5 and I I .6. The pipeline connection in the
tank should be located directly below the thief hatch and a minimum of 12 in.
above the tank bottom. Technical Data used in the field explained in petroleum courses in
Rawalpindi. It should be equipped with a valve and sealing device
immediately adjacent to the tank. Pipeline valves should be checked frequently
for leaks.Inlet connections preferably should be located in the deck of the
tank and should have a valve located near the inlet capable of closing off
against pressure.
Drain connections should be located immediately above the
tank bottom in the side of the tank or in the tank bottom immediately
adjacent to the side. They should be equipped with a valve and sealing device
located next to the tank. Drains from all tanks in a battery should be
connected together and piped well away from the tanks. Equalizer or overflow
connections should be installed below the deck in the tank shell. A valve and
sealing device should be installed immediately ad,jacent to the tank if more
than two tanks are in the battery and should be connected in such a manner that
any two tanks can be equalized together. Some more details of petroleum courses in
rawalpindi are as under.
Vent connections should be installed in the center of the
tank deck and all tanks connected to a common line. This line should have a
pressure-vacuum valve installed in the line or on the end of it. The line
should be sloped to prevent accumulation of liquids in it or in the valve. The
use of gas to roll stored products is usually considered poor practice, and
should be restricted to temporary or emergency use. If a roller line is used,
it should enter the tank through the deck and be equipped with a valve next to
the tank. TSK Training for Skills and Knowledge is the best institute in
Rawalpindi Islamabad for Pakistani Students who wants to join oil field after petroleum courses in
Islamabad.